Innovating with experience

ATG – L626 Giustizia interchange, BIASCA – SWITZERLAND

Client:

AlpTransit San Gottardo SA – Bellinzona

Cost:

33.30 Mio CHF

Date:

2011 – 2015

The project concerns one of the lots of the new railway line ATG in Biasca. The “Giustizia” interchange is the connection point between the already existing railway line Biasca-Osogna and the new railway line AlpTransit; it’s situated 7 km south of the Gotthard Base Tunnel’s portal. Different works have been achieved, such as: railway bridge over the Froda river/ Ofible channel, Giustizia tunnel, Stabiello channel and gravity concrete cofferdam, shifting of the existing railway line towards the mountains with rock fall protection and connection to the AlpTransit line, cantonal road’s modification and new emergency highway access, new cycle path with underpass.

Share